(1) In a case of non-performance the aggrieved party may by notice to the other party allow an additional period of time for performance.
(2) During the additional period the aggrieved party may withhold performance of its own reciprocal obligations and may claim damages but may not resort to any other remedy. If it receives notice from the other party that the latter will not perform within that period, or if upon expiry of that period due performance has not been made, the aggrieved party may resort to any of the remedies that may be available under this Chapter.
(3) Where in a case of delay in performance which is not fundamental the aggrieved party has given notice allowing an additional period of time of reasonable length, it may terminate the contract at the end of that period. If the additional period allowed is not of reasonable length it shall be extended to a reasonable length. The aggrieved party may in its notice provide that if the other party fails to perform within the period allowed by the notice the contract shall automatically terminate.
(4) Paragraph (3) does not apply where the obligation which has not been performed is only a minor part of the contractual obligation of the non-performing party.
Source: UNIDROIT
Imported:
- Here are your Documents and notes
- Create a new Document or Note using the toolbar above the legal text.
- Open an existing Document or Note from the right-hand column or directly in the text.
Documents
for Int. Privat- & Wirtschaftsrecht
notes
for ARTICLE 7.1.5 PICC
No notes available.